A can complete a piece of work in 10 days, and B can do the same work in 15 days. They work together for 5 days, and then C finishes the remaining work in 2 days. How long would C alone take to complete the entire work?
- A. 12 days ✓
- B. 14 days
- C. 18 days
- D. 16 days
Correct Answer: A. 12 days
Explanation
Work done by A and B in 5 days = 5 \times (\frac{1}{10} + \frac{1}{15}) = 5 \times \frac{5}{30} = \frac{5}{6}. Remaining work = 1 - \frac{5}{6} = \frac{1}{6}. C completes \frac{1}{6} work in 2 days, so C alone takes 2 \times 6 = 12 days to complete the entire work.
Related questions on Arithmetic
- Calculate compound interest on a sum of ₹ 64000 compounded quarterly for 1 year at a rate of 10%?
- A car owner or a man buys petrol at ₹ 8, ₹ 9 and ₹ 11 per litres for three successive years. What approximately is the average cost per litr...
- In a library 5 per cent books are in English; 10 per cent of the remaining are in Hindi and 15 per cent of the remaining are in Sanskrit. Th...
- (30\% \text{ of } 6500) \div 26 \div 25 = ?
- CP of 30 kg of rice is same as the SP of “X” kg of wheat. If shopkeeper makes profit of 20%, find X?