20 men are supposed to complete a work in 10 days. After working for 5 days, they realise that only one-fourth of the work is done. How many more men they need to employ to finish the work on time?

  1. A. 40
  2. B. 30
  3. C. 20
  4. D. 15

Correct Answer: A. 40

Explanation

Using M_1 D_1 / W_1 = M_2 D_2 / W_2, we substitute values: (20 \times 5) / (1/4) = (M_2 \times 5) / (3/4). Solving yields total men required M_2 = 60. More men needed = 60 - 20 = 40.