50 men can complete a work in 40 days. They begin the work together but a batch of 5 men left after each period of 10 days. What is the time to complete the work?

  1. A. 45 days
  2. B. 50 days
  3. C. 55 days
  4. D. 60 days

Correct Answer: B. 50 days

Explanation

Total work = 50 \times 40 = 2000 man-days. Work in 10-day periods: 500, 450, 400, 350. After 40 days, 1700 units are done. Remaining 300 units will be completed by 30 men in exactly 10 days. Total time = 50 days.