p number of men can finish a piece of work in q days. If there are 50% more men, then the work will be finished 12 days earlier. What is the value of q?

  1. A. 48
  2. B. 40
  3. C. 36
  4. D. Cannot be determined due to insufficient data

Correct Answer: C. 36

Explanation

The total amount of work is equivalent to p men working for q days, or p \times q man-days. If the workforce is increased by 50\%, the new number of men is 1.5p. Since they finish the work 12 days earlier, the new time taken is (q - 12) days. Equating the total work gives p \times q = 1.5p \times (q - 12). Dividing both sides by p yields q = 1.5q - 18, which solves to 0.5q = 18, making q = 36.